Do Wilgi
31.03.2025
Postęp pracy inwestycji Do Wilgi
Update:
- The reinforced concrete wall construction of 50% and the reinforced concrete slab under the garage entrance ramp at building B have been completed, as well as the reinforcement of
31.03.2025
Update:
31.03.2025
Update:
31.03.2025
Udate:
20.03.2025
Construction progress update:
12.03.2025
Structure and construction industry:
12.03.2025
In the construction industry:
12.03.2025
Structural and construction industry:
12.03.2025
In the general construction sector, the following work was carried out:
19.12.2024
Work progress:
04.12.2024
Finishing works:
14.06.2024
Work progress: On 13.06.2024, we obtained the Use Permit, which became effective on 14.06.2024.