Construction site logbook

Do Wilgi

31.03.2025

Postęp pracy inwestycji Do Wilgi

Update:

  • The reinforced concrete wall construction of 50% and the reinforced concrete slab under the garage entrance ramp at building B have been completed, as well as the reinforcement of

    Sprawdź

Do Wilgi

Takt Lirników

31.03.2025

Work progress of Takt Lirników

Update:

  • Excavation protection (steel sheet pile wall) 100% completed without soil anchors,
  • Part of excavation work with soil removal - 10% completed,
  • Wells for de

    Sprawdź

Takt Lirników

XYZ Place

31.03.2025

Work progress of XYZ Place investment

Udate:

  • Construction on +10 completed,
  • Masonry work underway - external walls on +7 and partition walls on +5,
  • Window joinery installation commenced on +5,
  • Roof

    Sprawdź

XYZ Place

Sady Żoliborz

20.03.2025

Work progress of Sady Żoliborz

Construction progress update:

  • Flooring on terraces/loggias completed,
  • balustrades on balconies/loggias completed,
  • false ceilings completed,
  • facade works comple

    Sprawdź

Sady Żoliborz

Apartamenty Portowa

12.03.2025

Work progress of Apartamenty Portowa

Structure and construction industry:

  • 100% of reinforced concrete walls of level P5 completed,
  • 80% of reinforced concrete walls of level P6 completed,
  • 70% of the ceiling

    Sprawdź

Apartamenty Portowa

Kameralny Prokocim 2

12.03.2025

Work progress of Kameralny Prokocim 2

In the construction industry:

  • Completion of internal plastering in flats,
  • Completion of internal plastering in the stairwell,
  • Carrying out flashings of attics and chimne

    Sprawdź

Kameralny Prokocim 2

Splot Wola

12.03.2025

Work progress of Splot Wola

Structural and construction industry:

  • Demolition and soil remediation was carried out on stage 1 and partially on stages 2 and 4,
  • Berliner wall protection of the excavation - all

    Sprawdź

Splot Wola

Żelazna 54

12.03.2025

Work progress of Żelazna 54

In the general construction sector, the following work was carried out:

  • vertical elements of storey +7 in 95%,
  • horizontal elements of the storey +7 in 70%,
  • prefabricated

    Sprawdź

Żelazna 54

Na Okrzei

19.12.2024

Work progress of Na Okrzei

Work progress:

  • We have obtained the Occupancy Permit,
  • Handover of flats to customers in progress.

Sprawdź

Na Okrzei

Sokratesa 11a

04.12.2024

Progress of work Sokratesa 11a

Finishing works:

  • landscaping works continued - DFA,
  • finishing work continued on common parts: filling, painting, interior finishing elements,
  • finishing works continued i

    Sprawdź

Sokratesa 11a

Na Bielany

14.06.2024

Work progress of Na Bielany

Work progress:
On 13.06.2024, we obtained the Use Permit, which became effective on 14.06.2024.

Sprawdź

Na Bielany