Construction site logbook

Żelazna 54

30.06.2025

Work progress of Żelazna 54

Update:

  • Reinforced concrete – completed,
  • Masonry works – completed,
  • Subfloor installations on level +2 – in progress,
  • Door frames – installation started,
  • Sprawdź

Żelazna 54

XYZ Place

30.06.2025

Work progress of XYZ Place

Update:

  • Plastering works are in progress on all staircases,
  • Facade works are in progress,
  • Installation of balcony railing brackets is in progress.
  • Installation

    Sprawdź

XYZ Place

Takt Lirników

30.06.2025

Work progress of Takt Lirników

Update:

  • Work related to securing the excavation has been completed,
  • 90% of the excavation has been completed,
  • Piling has commenced.

Sprawdź

Takt Lirników

Apartamenty Portowa

30.06.2025

Work progress of Apartamenty Portowa

Construction industry:

  • 100% of partition walls on level P7 completed,
  • Approx. 95% of thermal insulation of the ceiling in the garage at level -1 completed (garage system),
  • <

    Sprawdź

Apartamenty Portowa

Do Wilgi

30.06.2025

Work progress of Do Wilgi

Update:

  • Internal plastering completed 100% in segment A and segment B,
  • Floor screeds with acoustic insulation completed – segment A at level P0 and segment B at level P0,
  • Sprawdź

Do Wilgi

Sady Żoliborz

30.06.2025

Work progress of Sady Żoliborz

Update - Sady Żoliborz II:

  • excavation drainage continued,
  • foundation slab completed,
  • vertical elements of floor -2 completed,
  • reinforcement and concreting of w

    Sprawdź

Sady Żoliborz

Splot Wola

30.06.2025

Work progress of Splot Wola

Construction sector:

  • Completed vertical reinforced concrete structural elements on levels -2 and -1,
  • Completed the slab above the garage (above level -1) and ramps to ea

    Sprawdź

Splot Wola

Kameralny Prokocim 2

19.06.2025

Work progress of Kameralny Prokocim 2

Progress of works:
On 18 June 2025, we obtained the Occupancy Permit, which became valid on 19 June 2025.

Sprawdź

Kameralny Prokocim 2

Na Okrzei

19.12.2024

Work progress of Na Okrzei

Work progress:

  • We have obtained the Occupancy Permit,
  • Handover of flats to customers in progress.

Sprawdź

Na Okrzei

Sokratesa 11a

04.12.2024

Progress of work Sokratesa 11a

Finishing works:

  • landscaping works continued - DFA,
  • finishing work continued on common parts: filling, painting, interior finishing elements,
  • finishing works continued i

    Sprawdź

Sokratesa 11a

Na Bielany

14.06.2024

Work progress of Na Bielany

Work progress:
On 13.06.2024, we obtained the Use Permit, which became effective on 14.06.2024.

Sprawdź

Na Bielany